For First Time, TransCanada Says Tar Sands Flowing to Gulf in Keystone XL South

11:56 am in Uncategorized by Steve Horn

Cross-Posted from DeSmogBlog 

TransCanada admitted for the first time that tar sands oil is now flowing through Keystone XL‘s southern leg, now rebranded the Gulf Coast Pipeline Project. The company confirmed the pipeline activity in its 2014 quarter one earnings call.

Asked by Argus Media reporter Iris Kuo how much of the current 300,000-400,000 barrels per day of oil flowing from the Cushing, Oklahoma to Port Arthur, Texas pipeline is tar sands (“heavy crude,” in industry lingo), TransCanada CEO Russ Girling confirmed what many had already suspected.

“I don’t have that exact mix, but it does have the ability to take the domestic lights as well as any heavies that find a way down to the Cushing market, so it is a combination of the heavies and the lights,” said Girling. “I just don’t know what the percentage is.”

The Keystone Pipeline System — of which Keystone XL’s northern leg is phase four of four phases — is and always has been slated to carry Alberta’s tar sands to targeted markets. So the announcement is far from a shocker.

More perplexing is why it took so long for the company to tell the public that tar sands oil now flows through the half of the pipeline approved via a March 2012 Executive Order by President Barack Obama.

“Oil is Oil”

When DeSmogBlog reported TransCanada had begun injecting oil into the pipeline’s southern leg in December, the company would not reveal what type of oil it was.

“As you’ve likely seen me quoted before, oil is oil and this pipeline is designed to handle both light and heavy blends of oil, in accordance with all U.S. regulatory standards,” TransCanada spokesman Shawn Howard told DeSmogblog at the time.

I am not able to provide you the specific blend or breakdown as we are not permitted (by our customers) from disclosing that information to the media. There are very strict confidentiality clauses in the commercial contracts we enter into with our customers, and that precludes us from providing that.

Now, though, it appears the company has let the proverbial cat out of the bag.

“Texas Bound and Flyin’”

In the first quarter of 2014, Keystone XL’s southern half has opened up the floodgates for what was once a glut of oil in Cushing to reach Gulf Coast refineries at record levels.

To borrow the title of Jerry Reed’s 1980 country song classic, it’s “Texas Bound and Flyin.’” An April 17 Energy Information Agency communiqué lays out the dirty details.

“The main driver of the recent crude oil inventory builds on the [Gulf Coast] is start-up of TransCanada’s [Gulf Coast Pipeline] which runs from the Cushing, Oklahoma storage hub to the Houston area,” explained the EIA. “In late January, TransCanada completed the first delivery of crude oil via [Gulf Coast Pipeline] to [Gulf Coast] refineries.”

In short, the glut of oil has teleported from Cushing to Texas in the aftermath ofKeystone XL’s southern leg opening for business in January, as explained in another EIA March 27 update.

“Crude oil inventories at Cushing, Oklahoma, the primary crude oil storage location in the United States, decreased 13 million barrels (32%) over the past two months,” the EIA wrote. “On March 21, Cushing inventories were less than 29 million barrels, more than 20 million barrels lower than a year ago.”

Northern Leg and Rail

Keystone XL’s northern leg, or what many know simply as Keystone XL, also came up on the earnings call.

Girling voiced frustration with how long the process has taken and with President Obama’s April 18 announcement to delay a decision on the northern leg until after the 2014 mid-term elections.

“In our view this delay is inexplicable. The first leg of our Keystone system took just over 600 days to review and approve,” said Girling. “Now after more than 2,000 days, five exhaustive environmental reviews and over 17,000 cases of scientific data, the review process continues to be delayed.”

The prospect of moving tar sands oil by rail to Cushing was also discussed on the call.

Read the rest of this entry →

Dollarocracy: U.S. Congressmen Refuse to Address Keystone XL Southern Half Spill Concerns

2:00 pm in Uncategorized by Steve Horn

Cross-Posted from DeSmogBlog  

What’s the U.S. congressional response to the safety issues with the 485-mile southern half of TransCanada‘s Keystone XL pipeline raised by Public Citizen‘s Texas office? Mostly what Simon & Garfunkel called “The Sound of Silence” in their famous song.

DeSmogBlog contacted more than three dozen members of the U.S. Congress representing both political parties to get their take on Public Citizen’s alarming findings in its November investigation (including dents, metal that had to be patched up and pipeline segments labeled “junk”), but got little in the way of substantive responses.

Set to open for business on January 22approved via an Executive Order by President Barack Obama in March 2012 and rebranded the “Gulf Coast Pipeline Project” by TransCanada, the southern half of the pipeline has garnered far less media coverage than its U.S.-Canada border-crossing brother to the north, Keystone XL‘s northern half.

Over two dozen members of the U.S. House of Representatives wrote a letter to President Obama on December 12 expressing concern over the conflicts-of-interest in the U.S. State Department’s environmental review process for the northern half of the line.

But none of them would comment on concerns with the southern half of the line raised in the Public Citizen report after multiple queries via e-mail from DeSmogBlog.

Two to Tango

Only two out the dozens contacted offered somewhat substantive comments.

And one of them, U.S. Rep. Ralph Hall (R-TX) (Left), did not respond to the meat and bones of the question at hand. He did offer some oft-used industry talking points, though.

“The Keystone pipeline will create jobs and help reduce dependence on oil supplies from unfriendly nations,” Hall told DeSmogBlog. ”The State of Texas has a proven track record of successful oversight of the oil and gas industry, including pipelines, and I am confident that they will be diligent in ensuring the pipeline’s safety.”

Hall — who took $59,500 from the oil and gas industry before the 2012 elections and has already taken $12,500 for the upcoming 2014 elections — is far from a neutral stakeholder in the debate over anything pertaining to the petroleum industry.

“Since 2010, Hall has earned as much as $1 million from a company that holds mineral rights along the Barnett Shale,” explained a March 2013 Sunlight Foundation article. “The money was disclosed as dividends from a company called North & East Trading Co. (N&E).”

On the other side of the aisle, U.S. Rep. Gene Green (D-TX) (Right) also responded toDeSmogBlog‘s request for comment, offering more cautious words of support for the southern half of the pipeline’s commencement.

“Over the past decades, our interstate and intrastate pipeline systems have had remarkable safety records, unmatched by rail or highway modes of transportation,” Green stated. Read the rest of this entry →